继电保护与控制
一、保护基础 | Protection Fundamentals
二、保护功能类型 | Protection Functions
三、保护整定 | Protection Settings
四、控制系统 | Control Systems
五、光伏电站保护 | Solar PV Plant Protection
Protection Coordination — Settings and TCC Curves
Jiang, let's review the protection coordination for the solar farm. I want to see how you've coordinated the feeder relays with the main transformer and the grid interconnection.
江工,我们过一下光伏电站的保护配合。我想看馈线保护与主变压器和电网 互联是怎么配合的。
江工: Sure. Let me pull up the TCC curves. We have three levels of overcurrent protection: the feeder breakers on the 34.5 kV collector system, the main transformer secondary breaker, and the grid interconnection breaker at 230 kV.
好的。我调出TCC曲线。我们有三层过流保护:34.5 kV集电线路的馈线断 路器、主变压器二次侧断路器和230 kV电网互联断路器。
馈线保护用51反时限过流——极反时限曲线IEEE C3。启动值设为1.2倍满负荷 电流、约600A一次侧。时间倍率为0.3。这意味着在5倍启动值时——也就是 3000A——约0.5秒跳闸。
The feeder protection uses 51 inverse-time overcurrent — an extremely inverse curve per IEEE C3. Pick-up is set at 1.2× full load current, about 600A primary. Time dial is 0.3. That means at 5× pick-up — 3,000A — it trips in about 0.5s.
And the main transformer secondary relay? What's its curve?
主变压器二次侧继电器呢?什么曲线?
江工: 主变二次侧也是51,但用非常反时限曲线IEEE C1。启动值1.2倍变压器额定 电流,时间倍率0.5。这样馈线故障时馈线继电器先动作——馈线0.5秒而主变 1.2秒,有0.7秒的配合裕度。
The main transformer secondary also uses 51, but with a very inverse curve per IEEE C1. Pick-up 1.2× transformer rated current, time dial 0.5. So for a feeder fault, the feeder relay operates first — feeder at 0.5s vs main transformer at 1.2s, giving 0.7s of coordination margin.
同时还设了50速断——瞬动保护,启动值设为穿过变压器的最大故障电流的 1.3倍。这样它只对变压器内部故障动作,不会对馈线故障误动。
There's also a 50 instantaneous element — set at 1.3× the maximum through-fault current of the transformer. This way it only operates for transformer internal faults and won't misoperate for feeder faults.
Good coordination. What about the transformer differential?
配合得不错。变压器差动保护呢?
江工: 我们设了87T——变压器差动保护。动作值为0.3 pu,采用双斜率特性:斜率1 为25%到拐点2 pu,斜率2为60%以上。差动保护涵盖变压器整个区域——高压 套管CT到低压套管CT。跟51过流配合——差动对内部故障速动,过流做后备。
We have the 87T — transformer differential. Pick-up is 0.3 pu with a dual-slope characteristic: Slope 1 at 25% up to the knee point at 2 pu, Slope 2 at 60% beyond. The differential covers the entire zone from HV bushing CTs to LV bushing CTs. It coordinates with the 51 overcurrent — diff for fast internal faults, overcurrent as backup.
And the grid interconnection? The utility has their own requirements for anti-islanding and ride-through.
电网互联呢?电力公司有他们自己的反孤岛和穿越要求。
江工: 我们装了专用的电网保护继电器——有81频率保护(低频81L/高频81H)、59过 电压和27欠电压。反孤岛检测通过频率变化率和电压矢量偏移两个原理实现。 穿越设置:LVRT——零电压625ms不脱网,HVRT——1.2pu电压持续1秒。
We installed a dedicated grid protection relay — with 81 frequency (under 81L/over 81H), 59 overvoltage, and 27 under- voltage. Anti-islanding uses both rate-of-change-of-frequency (ROCOF) and vector shift. Ride-through: LVRT — zero voltage for 625ms without tripping, HVRT — 1.2 pu voltage for 1s.
Relay Commissioning — Injection Testing and Logic Verification
Feeder relay FDR-07 is installed, wired, and settings are downloaded. Now we'll inject secondary current and voltage with the relay test set to verify each protection function.
Test set connected. Simulating three-phase current. First, test 51 overcurrent — injecting 1.5× pick-up current... relay picks up at the calculated time of 2.1s, timer starts... trip contact closes. Operating time within 2% of TCC calculation. Pass.
Now test 50 instantaneous — injecting 10A (8,000A primary, above pick-up). Relay trips in 25ms — spec is within 30ms for instantaneous. Pass.
Test the directional element too — inject voltage and current for faults in forward and reverse directions. Confirm it trips for forward, doesn't trip for reverse.
While you're doing protection tests, I'm monitoring on SCADA. For every function tested, I see the events and alarms coming in correctly on SCADA. Trip signal, breaker status change, protection start — all timestamped correctly in the SOE. Protection-to-SCADA communication is working.
Finally, do the trip circuit supervision test — from relay trip contact all the way to the breaker trip coil. Relay sends trip command, auxiliary relay operates, trip coil energizes, breaker opens. The entire circuit is intact with no breaks.
Breaker position shows as "open" on SCADA. Interlock logic is also verified — breaker refuses to close when closing conditions aren't met.
All protection functions tested and passed. FDR-07 protection is ready for service. Next — main transformer relay FDR-01.