一、水电运维基础 | Hydropower O&M Fundamentals
二、水轮机维护 | Turbine Maintenance
三、发电机维护 | Generator Maintenance
四、辅助系统维护 | Auxiliary System Maintenance
五、水工建筑物维护与安全 | Civil Structure Maintenance & Safety
Characters: Maintenance Manager (检修经理 MM) / Mechanical Supervisor (机械主管 MS) · Characters: Dam Safety Engineer (大坝安全工程师 DE) / Operations Director (运行总监 OD)
Unit 2 has been running for 18,000 hours since the last major overhaul. The vibration levels at the turbine guide bearing have been trending up — from 45 μm to 78 μm over the past 6 months. The DGA on the thrust bearing oil showed elevated metal particles. It's time for the A-class overhaul. Let's plan the disassembly sequence.
2号机组自上次大修已运行18000小时。水导轴承振动水平在上升——过去6个月从 45μm到78μm。推力轴承油液DGA显示金属颗粒增多。该做A级检修了。规划拆卸顺序。
We start with the generator disassembly — disconnect the bus, remove the upper bracket, pull the rotor. Then the turbine: drain the spiral case and draft tube, remove the head cover, lift the runner and shaft as an assembly. The key inspection items: runner cavitation damage — we've repaired pitting on 7 of 13 blades in the last overhaul, let's see how the repairs held up. Guide vane end clearances — specification is 0.15-0.25 mm; if any gap exceeds 0.40 mm, we replace the wearing plates. Wearing rings on the runner and stationary parts — the radial clearance should be 0.8-1.2 mm; above 2.0 mm, we need re-machining or replacement.
从发电机拆起——断开母线、拆上机架、吊转子。然后水轮机:排空蜗壳和尾水管、 拆顶盖、转轮和主轴整体吊出。重点检查项:转轮空蚀破损——上次大修13个叶片有7个 做过补焊,看补焊效果如何。导叶端面间隙——规范0.15-0.25mm;超0.40mm换抗磨板。 转轮和固定部分止漏环——径向间隙应0.8-1.2mm;超2.0mm需机加工或更换。
And the thrust bearing? That's the most expensive single component to repair if it fails. We need to inspect the thrust pads — look for scoring, wiping, or babbit metal fatigue. Measure the pad thickness and compare with the as-built records. If any pad has lost more than 0.05 mm of babbit, we re-pour or replace. Also, the oil bath must be thoroughly cleaned and filtered — metal particles circulating in the oil will damage the new pads. I want the oil analyzed before and after cleaning to confirm zero particle count above 5 microns.
推力轴承呢?这是单个部件中坏了最贵的。需要查推力瓦——看有无划伤、烧瓦或 巴氏合金疲劳。测瓦厚度与竣工记录对比。任何瓦巴氏合金磨损超0.05mm就重浇或更换。 还有油槽必须彻底清洗过滤——油中循环的金属颗粒会损坏新瓦。清洗前后都要做油样 分析确认5微米以上颗粒数为零。
The rainy season forecast is out — the meteorological agency predicts 30% above-average precipitation in the catchment area over the next 3 months. We need to review the dam safety monitoring data and prepare the flood control plan. Let me walk you through the current monitoring readings.
雨季预报出来了——气象局预测未来3个月汇水区降雨量高于平均30%。需要审查大坝 安全监测数据、准备防汛方案。过一遍当前监测读数。
Go ahead. I'm particularly concerned about the seepage trend through the left abutment. Last season we had a slight increase there.
开始吧。特别关注左坝肩渗流趋势。上个雨季那里有轻微增加。
The seepage monitoring shows: total seepage through the dam body currently at 12 L/s — that's stable compared to the same period last year. The left abutment uplift pressure at piezometer P-12 is reading 0.32 MPa — that's actually 8% lower than last year, suggesting the grouting work we did in January has been effective. Displacement monitoring: the crest has moved 3.2 mm downstream from the zero reading — normal seasonal variation, well within the 15 mm warning threshold. Pendulum readings in the gallery show no anomalous deformation. Overall, the dam is in good condition.
渗流监测显示:坝体总渗流量当前12升/秒——与去年同期持平。左坝肩P-12测压管 扬压力0.32MPa——比去年低8%,说明1月份做的灌浆有效。位移监测:坝顶从零读数 向下游位移3.2mm——正常季节性变化,远在15mm预警阈值内。廊道正垂线无异常变形。 总体大坝状况良好。
That's reassuring. Now the operational plan for the rainy season: we need to pre-release water to bring the reservoir level from the current 245 meters down to the flood control level of 240 meters before the heavy rains arrive. That's about 18 million cubic meters to release through the turbines over the next 10 days — we can generate while lowering the level. At 240 meters, we have 45 million cubic meters of flood storage capacity. The spillway gates must be tested this week — open each of the 5 radial gates through a full cycle and verify the emergency power supply for gate operation.
这放心了。雨季运行方案:需要预泄把库水位从当前245米降到汛限水位240米等待 大雨。约1800万方水通过水轮机10天内放掉——边发电边降水位。240米时有4500万方 防洪库容。溢洪道闸门本周须测试——5扇弧形闸门全开全关各一个循环、验证闸门操作 的应急电源。